Planned Settlement: July/August 2024

Civil construction has progressed well through the month of May with the majority of the civil works now complete.
The asphalt on the internal roads is on schedule to be finalised in early June, with the electrical works to be completed shortly after.
Once the asphalt is complete, this will allow Naturform to begin the hardscape landscaping, which includes the driveway crossovers and footpaths.
Latest Construction Update