The Quarry Construction Update – Release Three


04 September 2024

 

Settlement Forecast: September 2024

On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.

Construction Progress: Construction Underway
On Track

Welcome to your September construction update for Release Three at The Quarry.

Civil works are now 90% complete with earthworks and roadworks now finalised. Landscaping contractor Naturform has now completed all driveway crossovers, which has allowed for soft landscaping to commence.

We hope you enjoy the recent drone image from site, showing just how much progress has been made in the last few weeks.

We are excited to share that Plan Sealing of Stage 3 has now been achieved. Title Registration for Stage 3 has now been lodged and your land remains on schedule to settle in late September. Our focus remains on quality and program as we work closely with our contractor to ensure we can settle your property as soon as possible. Should there be any change to this timing, our Customer Care team will be in contact with you. If obtaining finance, please ensure your financier is prepared for settlement.


Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

We're available to discuss any questions or concerns you may have regarding your coming settlement.

Book your appointment now


See more construction updates on



You may also like