Ed.Square Construction Update - Brooklyn Row - Block 2 (BE Homes)
We are pleased to bring you an update on your home in Brooklyn Row Block 2.
We have seen wonderful progress on-site recently.
Block 2 bin bays
Lots 13022-12033: Block work to planter boxes in the podium courtyards are now 95% complete. Internally, tiling fit off is almost complete with plasterboard quality assurance currently underway for the second coats of paint to be applied. This will see carpet installation commence in the coming week.
Block 2 courtyards
Lots 13034-13045: Scaffold dismantling is now complete which has seen blockwork to front walls and bin bays well underway. Preparation for podium waterproofing have begun. Internally, joinery and tiling installation is well advanced. This will see fit off works commence in the coming week.
Block 2 kitchen installation
Based on the current construction program, inspections and settlements forecast to occur in Late Quarter 3 2023.
The anticipated completion dates are based on the current program and are reviewed on a regular basis to ensure we deliver a quality outcome. From time to time, there will be movement in these dates to allow for unforeseeable events such as extreme weather.
Site Safety
We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.
If you have any queries about your home, please reach out to CustomerCareNSW@frasersproperty.com.au or call 13 86 88.