Ed.Square Construction Update - Brooklyn Row - Block 2 (BE Homes)


11 May 2023

We are pleased to bring you an update on your home in Brooklyn Row Block 2.

We have seen wonderful progress on-site recently.



Block 2 Internal


Block 2 Courtyard

Lots 13022-12033: Scaffold has been dismantled. This allows the block layers to start setting out front walls and bin bays. Podium planters and arbour installations have commenced. Internally, kitchen cabinetry is installed with bench top installations now underway. Tiling works to balconies have commenced.



Block 2 Mews


Block 2 Block Work

Lots 13034-13045: Scaffold has been dismantled. This allows the block layers to start setting out front walls and bin bays. Podium planters and arbour installations have commenced. Internally, kitchen cabinetry installations are underway, with main floor tiling complete, architraves well advanced and waterproofing complete to balconies and wet areas.

Based on the current construction program, inspections and settlements forecast to occur in Late Quarter 3 2023.

The anticipated completion dates are based on the current program and are reviewed on a regular basis to ensure we deliver a quality outcome. From time to time, there will be movement in these dates to allow for unforeseeable events such as extreme weather.

If you have any queries about your home, please reach out to the Customer Care Team at CustomerCareNSW@frasersproperty.com.au or by calling 13 86 88.


Brian Halpin Customer Care Coordinator Frasers Property Australia