Ed.Square Construction Update - Brooklyn Row - Block 2 (BE Homes)
We are pleased to bring you an update on your home in Brooklyn Row Block 2.
We have seen noticeable progress onsite since our last update.
Lots 13022-12033: Render, applied finishes, screens and balustrade installation are nearing completion. This will see dismantling of the scaffold commence in the coming weeks. Stair Installation is now complete along with tiling to level 1, this will see joinery installation commence and tiling to remaining levels.
Lots 13034-13045: Façade cladding is complete, with rendering and applied finishes well underway along with stair installation. This will see waterproofing now commence along with balcony screens and balustrade installation.
Based on the current construction program, inspections and settlements forecast to occur in Quarter 3 2023.
The anticipated completion dates are based on the current program and are reviewed on a regular basis to ensure we deliver a quality outcome. From time to time, there will be movement in these dates to allow for unforeseeable events such as extreme weather.