Ed.Square Construction Update - Brooklyn Row - Block 2 (BE Homes)


13 July 2023

We are pleased to bring you an update on your home in Brooklyn Row Block 2.

We have seen wonderful progress on-site recently.


Block 2 podium waterproofing underway

Lots 13022-12033: It's great to see the carpet installation is now complete, along with the second coat of paint. This has led the site team to commence quality checks. Early landscaping works have now commenced. Rear courtyards have had waterproofing commence and arbours installed.


Block 2 Mews side facades

Lots 13034-13045: Internally, plasterboard first coat is complete, and painters have commenced the second coats in preparation for carpet installation to commence. Rear courtyards have had waterproofing commence and arbours installed.


Block 2 kitchen installation

Based on the current construction program, inspections and settlements forecast to occur in Late Quarter 3 2023.

The anticipated completion dates are based on the current program and are reviewed on a regular basis to ensure we deliver a quality outcome. From time to time, there will be movement in these dates to allow for unforeseeable events such as extreme weather.

Site Safety

We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.

If you have any queries about your home, please reach out to CustomerCareNSW@frasersproperty.com.au or call 13 86 88.


Brian Halpin Customer Care Coordinator Frasers Property Australia