Certificates of Title: February 2025

Works are on schedule. Earthworks are complete and retaining walls are 65% completed. Sewer is well advanced 90% complete as is drainage and water reticulation is 30% complete. Underground cable laying has commenced and is 60% complete. Communication ducting is 20% complete.
The adjoining nature playground and parkland is complete. Built along the edge of the Serpentine tributary with core steel decorative animal/bird watching hides, sheltered seating, and meandering pathways through the trees.

Earthworks are now complete.
Practical Completion anticipated in November 2024.
Nature playground is complete and ready for the community to enjoy
Latest Construction & Community Update

 



Track another property

card icon

SOLD OUT

Rivers Edge Stage 3

Certificates of Title available

Track property

card icon

SOLD OUT

Forest Walk Stage 4B

Certificates of Title expected February 2025

Track property

card icon

SOLD OUT

Forest Walk Stage 7

Certificates of Title Available

Track property

card icon

SOLD OUT

Forest Walk Stage 8

Certificates of Title Available

Track property

card icon

SOLD OUT

Completed Stages

For build documents on completed stages please follow the link

Build information