To assist you on your property journey we have developed this tracker that can guide you on all the important milestones from when you sign the contract, to construction and reaching a settlement and beyond. Click on the phases below or click and drag left and right to scroll through the milestones.



Disclaimer: Whilst Frasers Property has tried to ensure that the tracking status is up to date, the content provided is ‘as is’ and ‘as available’ and is subject to change.

Certificates of Title: September 2025

Rivers Edge Stage 5 is a large stage of 58 lots. It’s the final stage in the Rivers Edge precinct. Bulk earthworks and installation of sewer services has commenced. Some necessary enhancements to the sewer design have been required, which will likely result in a program delay of one month.

Works commenced in mid December.
Practical completion now planned for August 2025.
3 parks and foreshore works to commence following completion of Stage 5.
Latest Construction & Community Update

 



Recent Rivers Edge - Stage 5 Updates

It's all here to keep you up to date with the latest news and updates about Rivers Edge - Stage 5.

View Updates

Track another property

card icon

SOLD OUT

Rivers Edge Stage 4

Certificates of Title expected March 2025

Track property

card icon

SOLD OUT

Forest Walk Stage 4B

Certificates of Title expected February 2025

Track property

card icon

SOLD OUT

Forest Walk Stage 9

Certificates of Title expected August 2025

Track property

card icon

SOLD OUT

Completed Stages

For build documents on completed stages please follow the link

Build information