Shell Cove Construction Update - Sands Homes
The Sands Aerial View
Welcome to the latest Construction Update.
We’re pleased to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.
This month, we’re pleased to advise that we have partnered with OpenSpace, a platform that captures on-site photography and provides an interactive view of the construction progress of your home. We hope you find this new tool valuable. Click here to take an inside view now.
We are pleased to report significant progress continues on The Sands homes. The following milestones have been achieved over the last month:
- The installation of the upper frame and roof trusses has been successfully completed for all remaining homes.
- Services rough-ins have been fully completed for all homes to ensure all necessary infrastructure is in place.
- The installation of fascia, gutters, and roof sheeting has been completed for all homes, providing a finished look and necessary weatherproofing.
- Skylights have been installed in all homes.
If you have any questions, reach out to our dedicated Customer Care team.
Settlement Update
Settlement is anticipated for quarter 1, 2025.
The Sands Progress July 2024
Site Safety
We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.