Shell Cove Construction Update - Sands Homes
The Sands September 2024
Welcome to the latest Construction Update.
We’re pleased to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.
This month, we’re pleased to advise that we have partnered with OpenSpace, a platform that captures on-site photography and provides an interactive view of the construction progress of your home. We hope you find this new tool valuable. Click here to take an inside view now.
The team has been working hard and making great progress on your new home. Over the past month, the following milestones have been achieved:
- Scaffold removal is complete for the fonzies and garages.
- Internal linings have begun for the fonzies.
- Consultants have conducted pre-lining inspections for major services in homes 3004 to 3008.
We’re excited to keep you updated as construction moves forward!
If you have any questions, reach out to our dedicated Customer Care team.
Settlement Update
Settlement is anticipated for Quarter 1, 2025.
Site Safety
We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.