Shell Cove Construction Update - Sands Homes
The Sands Aerial View | February 2025
Welcome to the latest Construction Update.
We’re pleased to keep you informed about how the project is progressing, give you insights into the construction process and ensure you are up to date with the development of your new community.
Construction has been back on track after the Christmas closure and things are progressing well at The Sands.
- Homes 3001 – 3003: Tiling has been completed with the kitchens, benchtops, and fixtures to be installed next, bringing the homes closer to completion. Not too much longer to go now as these homes enter their final stages, transforming into beautifully finished spaces.
- Homes 3004 – 3006: These homes are nearing completion, with the remaining fit-offs for services, fixtures, shower screens and carpet underway. Following with landscaping which will transform the exterior and the cleaning is set to begin by the end of the month.
- Homes 3007 – 3008: These homes are nearing completion and have begun the builder’s clean, showcasing their true beauty. The electricity is on, the lights are shining, and landscaping is underway, set to transform the final appearance.
We look forward to keeping you updated as The Sands Homes continue to progress.
If you have any questions, please reach out to our dedicated Customer Care team.
Settlement Update
Settlement is now anticipated for March - April, 2025.
Site Safety
We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.