Shell Cove Construction Update - Sands Homes
The Sands Aerial View October 2023
Welcome to the latest construction update.
We’re excited to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.
The internal and external drainage work for CN3001-3003 has been successfully completed.
The installation of connecting services between garages and the main dwellings in CN3001-3003 are now finished.
The backfilling of retaining walls has been completed, providing stability and support to the projects structure.
Formwork has been initiated for CN3004-3006 along with the commencement of frames and structural steel for CN3007-3008, ensuring the integrity and strength of these buildings.
Upcoming Works:
- Finish pouring slabs CN3001-3006
- Commence formwork CN3001-3003
- Commence frames and structural steel for CN3004-3006
Settlement is anticipated for quarter 4, 2024.
Site Safety
We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.
See more construction updates on