Ed.Square Construction Update - Chelsea Pocket Block D


21 November 2022

We are pleased to update you on the progress of your new home in Chelsea Pocket at Ed.Square.

Lots 12001-12012: Eastern wing internal quality inspections have commenced with the rear courtyard tiling now underway. Landscapers have started onsite with works to footpaths and paving.

Lots 12013-12024: Western wing internal tiling is now complete with the team doing preparation works for painting to commence.

Based on the current construction program, inspections are forecast to commence in December 2022 with settlements forecast to commence in late January 2023.

The anticipated completion dates are based on the current program and are reviewed on a regular basis to ensure we deliver a quality outcome. From time to time, there will be movement in these dates to allow for unforeseeable events such as extreme weather.

If you have any queries regarding your home, do not hesitate to reach out to us via email at ProsperityCareNSW@frasersproperty.com.au or by phone on 13 86 88.

221205_Ed CP Block 3


Brian Halpin Customer Care Coordinator Frasers Property Australia