Shell Cove Construction Update - Reflection Homes


14 March 2025
Stage Reflection

Reflection Homes – March 2025

Welcome to the latest construction update.

We’re pleased to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.

We are excited to share the latest progress on the Reflection Homes project. Our teams have been making significant strides, and we are pleased to provide the following updates:

Homes 3101–3102
  • External façade works, including cladding, flashings, painting, and downpipes, are being finalised to ensure durability and a modern aesthetic.
  • Internal carpentry fix-out has commenced.
Homes 3103–3105
  • External façade works have been completed, enhancing the homes' visual appeal and weather resistance.
  • Balustrades and feature screens have been installed, adding architectural interest and privacy.
  • Stripped scaffolding in preparation for external groundworks.
  • Internal carpentry fix-out has been completed.
  • Installation of kitchens and cabinetry has commenced, bringing the interiors closer to completion.
  • Internal tiling works to wet areas and living spaces have commenced where required, adding to the finishing touches.
3106–3108
  • External façade works have been completed, contributing to the overall streetscape appeal.
  • Balustrades and feature screens have been installed, providing both functionality and style.
  • Stripped scaffolding in preparation for external groundworks.
  • Internal carpentry fix-out has commenced, ensuring all interior timber works are progressing as planned.
  • Internal tiling works in wet areas and living spaces have commenced where required, bringing definition to key areas of the home.
Homes 3109–3111
  • External façade works have been completed, finalising the external structure of the homes.
  • Balustrades and feature screens have been installed, refining the homes' exterior detailing.
  • Stripped scaffolding in preparation for external groundworks.
  • Internal carpentry fix-out has been completed, ensuring all structural and finishing elements are in place.
  • Internal tiling works have been completed in wet areas and living spaces where required, marking another step toward completion.
Homes 3112–3114
  • Service rough-ins continue, ensuring essential plumbing, electrical, and mechanical systems are properly integrated.
  • Finalising external façade works, including cladding, flashings, painting, and downpipes, to complete the homes' exteriors.

Stage Reflection
Reflection Aerial View

Stage Reflection
Facades taking shape

Stage Reflection
Internal progress - fonzie

Stage Reflection
Progress – garage under fonzie

Stage Reflection
Internal progress

Stage Reflection
Internal progress

Stage Reflection
Internal progress

Stage Reflection
Internal progress

Stage Reflection
Internal progress

Stage Reflection
Internal progress

Stage Reflection
Internal progress

Stage Reflection
Internal progress

Stage Reflection
Internal progress

Stage Reflection
Internal progress

Stage Reflection
Internal progress

Our team remains dedicated to delivering your home with the highest quality standards. Should you have any questions or require further information, please do not hesitate to contact our Customer Care team.

Settlement Update

We anticipate settlements to occur from Quarter 3, 2025.

Site Safety

We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.


Silvana Stojanovski Customer Care Coordinator Frasers Property Australia