Shell Cove Construction Update - Ancora Apartments
Building B & C
The first round of Frasers Property Quality Assurance inspections, commonly known as "QA", began in late May for the ground floor apartments of Building B. QA Inspections are now at Level 2 in Building B, and Ground Floor in Building C. QA inspections mark the completion of all internal work within these apartments, with only minor incomplete works and touch-ups left to address. Commencing QA is the first step in our meticulous process to ensure the apartments are delivered to a high-quality standard.
Frasers Property Quality Assurance inspections will continue through the upper floors of Building B and then move to Building C in the coming weeks.
While the apartment interiors are nearing completion, common areas such as corridors, lift lobbies, and basement plant rooms are in their final stages, including the final coat of paint and flooring transitions.
Building A
In Building A, joinery has been installed on levels 1 and 2, with level 3 scheduled to receive its delivery in the first week of June. Stone installations for these levels are closely following, with levels 1 and 2 measured and scheduled for installation during the first two weeks of June. Living room timber and tiling are complete except for the ground floor, which is expected to be finished in the coming weeks.
Building A Level 1 Kitchen Progress
Building A Level 2 Kitchen Progress
Building A Level 3 Kitchen Progress
External Works
Externally, paving and mass planting around Buildings B and C are approximately 90% complete, including most of the ground floor balcony fencing. Along the wetlands elevation, we have begun constructing the sandstone block retaining wall, which will create a seamless transition between the buildings and the wetlands footpath. The use of sandstone integrates this space with the materials used throughout the area.
The dismantling of the scaffolding around Building A commenced at the end of May, and is expected to be fully completed within 2-3 weeks. This is a significant milestone for the project as it allows for the waterproofing and paving of the ground floor balconies, as well as the commencement of landscaping, stairs, and pavements.
Settlement Update
We anticipate settlements to occur from September 2024through to October 2024.
The below table outlines more detailed information on forecasted timings for when key milestones are anticipated to occur in the lead up to construction completing within each building, as well as forecasted timings to prepare for settlement of your apartment.
These forecasted timings will be reviewed as construction continues to progress and as we get closer to preparing your apartment for settlement.
ANCORA PROGRAM AND TIMINGS |
BUILDING A |
BUILDING B |
BUILDING C |
Construction Phase |
|||
Kitchens and Joinery Installation |
Early to mid July 2024 |
Complete |
Complete |
Frasers Property Quality Assurance Inspections |
Commence from mid July 2024 |
Underway - up to level 2 |
Underway - at Ground Floor |
External Works |
Late August 2024 |
Mid August 2024 |
Mid August 2024 |
Pre-settlement Phase |
|||
Strata Plan Registration |
August 2024 |
August 2024 |
August 2024 |
Pre Settlement Inspection Invitations |
Late August 2024 |
Late July 2024 |
August 2024 |
Pre Settlement Inspections |
September 2024 |
August 2024 |
August 2024 |
Valuations |
Throughout September 2024 |
Throughout Ausgust 2024 |
Throughout Ausgust 2024 |
Occupation Certificate |
August 2024 |
August 2024 |
August 2024 |
Settlement Phase |
|||
Forecasted settlement timing |
Late Sept to October 2024 |
September 2024 |
September 2024 |
If you have any questions, our Customer Care team are available.
Site Safety
We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.
See more construction updates on