Shell Cove Construction Update - Reflection Homes
Reflection Homes – April 2024
Welcome to the latest Construction Update.
We’re pleased to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.
We are thrilled to inform you that significant progress has been achieved on the Reflection Homes project.
The installation of ground floor frames has already commenced, with Lots 3101 to 3108, including Lot 3101 Fonzie, installed.
Ground floor framing has commenced
Additionally, preparation for main housing slabs for Lots 3109 to 3114 is currently underway and will be poured in the coming weeks.
Several activities have been scheduled to take place by mid-month:
- Lots 3101 to 3108 – will see the installation of level one floor systems.;
- Lots 3103 to 3108 garages – the pouring of concrete wet walls is planned;
- Lots 3109 to 3111 – main housing slabs will be poured during this time as well.
Furthermore, the following activities are scheduled to occur in the coming weeks:
- Lots 3101 & 3102 fonzie’s/garages – brickwork will commence;
- Lots 3103 to 3108 – brickwork will also commence;
- Lots 3109 to 3111 – garage slabs will be poured;
- Lots 3109 to 3111 – termite barrier installation will commence.
We are excited about the continued progress and are dedicated to delivering a high-quality result. If you have any questions or require further information, please do not hesitate to reach out to us.
Site Safety
We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.