Shell Cove Construction Update - Sands Homes


07 December 2023

The Sands Aerial View

Welcome to the final construction update of 2023!​

We’re pleased to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.

This month, we’re pleased to advise that we have partnered with OpenSpace, a platform that captures on-site photography and provides an interactive view of the construction progress of your home. We hope you find this new tool valuable. Click here to take an inside view now.

All lot slabs have now been successfully poured, laying a strong foundation for your new home. The ground floor framework has continued across the stage.

Looking ahead to the holiday season, the lower brickwork and first-floor framing are set to continue before Christmas. This anticipated progress ensures that your home is taking shape according to schedule, and we are dedicated to keeping the momentum going into the new year.

Settlement is anticipated for quarter 4 2024.


The Sands Slabs Poured

The next construction update will be sent to you in the new year in February, 2024.​

For now, on behalf of the Customer Care Team, we'd like to wish you a safe and happy holiday season!​

Site Safety

We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.


Laura Struys Customer Care Coordinator Frasers Property Australia
Silvana Stojanovski Customer Care Coordinator Frasers Property Australia