Shell Cove Construction Update - Sands Homes
The Sands Aerial View November 2023
Welcome to the latest Construction Update.
We’re excited to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.
The internal and external drainage work for all properties has now been successfully completed.
The installation of connecting services between garages and the main dwellings in CN3001-3003 has been finalised, enhancing the functionality and accessibility of the structures.
The backfilling of retaining walls has been successfully accomplished. This achievement provides essential stability and support to the projects overall structure.
Completion of the installation of CN3004-3006 slab. Ground floor framing for units 3008-3004 is well underway, marking significant progress in the construction process.
Looking ahead, the next key steps are:
- Finish pouring slabs for Lots CN3001-3003.
- Commence the ground floor frames for CN3001-3003.
- Commence brickwork around the garages.
Site Safety
We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.
See more construction updates on