Shell Cove Construction Update - Reflection Homes
Reflection Homes – July 2023
Welcome to the latest Construction Update
We are excited to keep you informed of how the project is progressing, and to give you insights into the construction process to keep you up to date with the development of your new community!
We are pleased to advise that site works have now commenced and are off to a good start! Our team has successfully completed the benching pads to ensure proper leveling, as well as the excavation for the footings of the external retaining wall.
This includes establishment of full site fencing, implementation of sediment and erosion control measures as well as commencement of initial earthworks and lot benching.
Moving forward, we have planned several upcoming works to continue the project's momentum. This includes the installation of service lead-ins, blinding slabs for the footings, installation of reinforcement cages for the retaining wall footings, and pouring the retaining wall footings themselves. These activities will lay the foundation for the external structures, ensuring stability and functionality.
At this stage completions and settlements are anticipated at the end of 2024. We appreciate your continued support as we work diligently to bring your project to life. If you have any questions or require further information, please do not hesitate to contact our team.
Site Safety
We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.