Botanica Construction Update - The Mews
Welcome to your November construction update from The Mews at Botanica.
Site Update
It has been a busy month onsite, and despite some rain delays, important progress has been made.
The provision of services (water, electricity, gas, NBN, sewer, stormwater) has been completed. As you can see in the drone photo, the blockwork has commenced for the retaining walls. The coming month should see a very exciting milestone with the pouring of the first concrete slab.
Settlement Forecast
We are currently forecasting The Mews for completion and settlement by the second half of 2025. This forecast is subject to weather delays, general construction progress, and receipt of the title registration and occupation certificates.
Contact Us
We will continue to update you every month as construction progresses, but in the meantime, if you have any questions, please do not hesitate to email customercarensw@frasersproperty.com.au or call 13 86 88 or +612 9767 2297.