To assist you on your property journey we have developed this tracker that can guide you on all the important milestones from when you sign the contract, to construction and reaching a settlement and beyond. Click on the phases below or click and drag left and right to scroll through the milestones.



Disclaimer: Whilst Frasers Property has tried to ensure that the tracking status is up to date, the content provided is ‘as is’ and ‘as available’ and is subject to change.

Titles Expected: May 2025

Summary: Works for The Peninsula (Stage 9) are progressing on program. The Waterfront Park design is well progressed with final design approvals underway and works due to commence in March/April 2025.

Drainage works have commenced as have common services.
Retaining walls are well advanced.
Practical Completion is on track for mid April to early May 2025.
Latest Community & Construction Update



Track another property

card icon

SOLD OUT

Onyx Lane

Certificates of Title available

Track property

card icon

NOW SELLING

Omeo Edge

Certificates of Title available

Track property

card icon

SOLD OUT

Completed Stages

For build documents on completed stages please follow the link

Build information