Bradmill Yarraville Construction Update - Pioneer Townhomes 1A
- Settlement Forecast: Q4 2025
On Track
- Construction Progress: Construction in progress
-
On Track
Stage 1A : Pioneer Townhomes
We are pleased to provide the following update on your home’s construction progress: scaffolding has been erected on all homes, enabling the commencement of external façade work. Additionally, all roofs have been installed. Solar panels have begun to be installed on homes 101-105.
Furthermore, electrical and plumbing rough-ins have now started, moving us closer to plasterboard installation.