myFrasersProperty 13 38 38
myFrasersProperty 13 38 38

Bradmill Yarraville Construction Update - Pioneer Townhomes 1A


27 November 2024
Settlement Forecast: Q4 2025

On Track

Construction Progress: Construction in progress
On Track
Stage 1A : Pioneer Townhomes

We are pleased to update you on the progress of the project: Underground services have now been completed across the stage and 95% of the slabs for Stage 1A homes have been successfully poured, and the ground floor frames of 8 homes are now erected. Frasers Property is actively coordinating with our partner builder to procure all necessary elements, while thoroughly reviewing every detail to ensure the high standards are met.


Tina Wu Senior Customer Care Consultant Melbourne

See more construction updates on



You may also like