29 January 2025
Settlement Forecast: Q4 2025

On Track

Construction Progress: Construction in progress
On Track
Stage 1B : Pioneer Townhomes

We’re excited to share that all concrete slabs in Stage 1B have now been poured, marking an important milestone in the project. Additionally, termite treatment has been completed on all homes.

We’re moving forward with the installation of ground floor frames, and structural steel work is on track to be completed by the end of this month.

We're continuing to make great strides and will keep you informed of further developments as construction progresses.


Tina Wu Senior Customer Care Consultant Melbourne