Midtown Construction Update - SOUL Residences
Welcome to the February construction update for Soul Residences at Midtown MacPark.
It has been a busy start to the new year, as we approach the later stages of construction.
- Levels LG up to 11 - the apartments are mostly complete, and the team is working through our quality assurance processes with the builder.
- Levels 12-14 - The final fit-off of services (plumbing and electrical) is underway.
- Levels 15-18 - Joinery, benchtops and splashback installations are in progress.
- Rooftop - Installation of services plant continues along with landscaping works.
The private central courtyard is transforming with walls, paving, and landscaping works being installed.
Elsewhere at Midtown MacPark, there has been significant work in the public areas in preparation for first residents. This includes footpath paving, landscaping, and the installation of mature trees.
Settlement Forecast
We currently anticipate settlements of Soul Residences to commence in April 2024. This forecast is subject to construction progress, weather delays and receipt of title registration and the occupation certificate.
As we get closer to completion, we will provide you with further information and schedules for the key steps prior to settlement, in particular the valuation appointments and the pre-settlement inspections.
We will continue to update you every month as construction progresses, but in the meantime, if you have any questions, please do not hesitate to email customercareNSW@frasersproperty.com.au or call 13 86 88 or +612 9767 2297.
See more construction updates on