Five Farms Construction Update – Stage 26


29 January 2025

 

Settlement Forecast: Late February 2025

On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.

Authority Approvals and Practical Completion in progress
On Track

Construction is now fully complete on site, and all Authorities have issued their consent for the Statement of Compliance. We are now working with Council to finalise the last of the Planning Permit requirements, so they can issue Statement of Compliance.

Once Statement of Compliance is issued by Council, we can then lodge the Plan of Subdivision with the Titles Office, so that Titles can be issued.

With settlements fast approaching, we strongly recommend that Purchasers ensure finance is in place, so that they are prepared for settlement, allowing this process to run as smoothly as possible.


Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

We're available to discuss any questions or concerns you may have regarding your coming settlement.


Customer Care VIC Frasers Property Australia

See more construction updates on



You may also like