Berwick Waters Construction Update - Stage 9


24 January 2025

 

Settlement will occur on August 2025 – October 2025

On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.

Construction Milestone: In progress
On Track

The water main and gas main construction along the intersection of Thompsons Road and Crosswater Boulevard are now complete. Drainage along the intersection has now commenced.

Bulk earthworks have commenced on the northern section of the bridge.

The road subbase preparation has commenced within the stage 9 internal to prepare the roads. Kerb and channel to follow.

The Bridge works are progressing well with the abutments under construction and rock beaching to follow.


Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

We're available to discuss any questions or concerns you may have regarding your coming settlement.


Customer Care VIC Frasers Property Australia

See more construction updates on



You may also like