Berwick Waters Construction Update - Stage 9
- Settlement will occur on August 2025 – October 2025
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.- Construction Progress: In progress
-
On Track
The water main and gas main construction along the intersection of Thompsons Road and Crosswater Boulevard has commenced.
Internal Sewer is now complete. Drainage is 95% complete.
Subgrade preparation of the roads are underway with conduits for services to follow.
Construction of the bridge earthworks in preparation for piling have commenced.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on