myFrasersProperty 13 38 38
myFrasersProperty 13 38 38

Berwick Waters Construction Update - Stage 9


11 December 2024

 

Settlement will occur on August 2025 – October 2025

On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.

Construction Progress: In progress
On Track

The water main and gas main construction along the intersection of Thompsons Road and Crosswater Boulevard is nearing completion.

Internal Sewer and drainage is now complete.

Water service installation has commenced and will continue through to Christmas along with road subgrade works.

Bridge earthworks are complete and ready for bridge piling works to commence prior to Christmas while off site fabrication of bridge elements is underway.


Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

We're available to discuss any questions or concerns you may have regarding your coming settlement.


Customer Care VIC Frasers Property Australia

See more construction updates on



You may also like