Shell Cove Construction Update - Nautilus Apartments
Nautilus – August 2024
Welcome to the latest Construction Update.
We’re pleased to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.
Building A
Internal fit-out works are being finalised with the installation of the final joinery elements. The final painting is occurring from west (core A1) to east (core A5), and is nearing completion.
Initial Pre-Settlement inspections (PSI) are now underway in cores A1, A2 and A3 with finishes and cleaning crews working through the remaining apartments in preparation for PSI bookings.
Quality Assurance inspections by the Frasers Property team have now been completed to all apartments. These inspections are an integral part of our commitment to delivering a high-quality project that meets industry standards.
Building A – GF Core A3 entrance
Building A - kitchen
Building A – ensuite
Building A – living area
Building A – L5 balcony view
Building A - laundry
Building B
Occupation Certificate has been received and settlements are being called in a staged manner.
Building B – alternate kitchen style
Building B – living area
Podium & verge works
All final asphalt layers have now been placed with line marking and road signage installed. The final perimeter fence is ready for removal.
The Contractor has removed the temporary site accommodation as we ready for occupation by new residents.
Inspections by the building certifier and the fire brigade are complete and closed-out. The Occupation Certificate has been received.
Nautilus Pool
Nautilus in the twilight
Southern elevation
The building’s lights illuminate the night
Settlement Update
We anticipate settlements to occur from August 2024 through to September 2024.
The below table outlines more detailed information on forecasted timings for when key milestones are anticipated to occur in the lead up to the settlement of your apartment in both Building's A and B.
Rotate your device: Please rotate your device to landscape mode for the best viewing experience of this table. This will ensure all details are clearly visible and the table is easier to navigate.
NAUTILUS PROGRAM AND TIMINGS |
BUILDING A |
BUILDING B |
Construction Phase |
||
Kitchens and Joinery Installation |
Complete |
Complete |
Frasers Property Quality Assurance Inspections |
Complete |
Complete |
External Works |
Complete |
Complete |
Pre-settlement Phase |
||
Strata Plan Registration |
Registered |
Registered |
Pre Settlement Inspection Invitations |
Underway |
Complete |
Pre Settlement Inspections |
August 2024 |
Complete |
Valuations |
Underway - book in now |
Complete |
Occupation Certificate |
Achieved |
Achieved |
Settlement Phase |
||
Building B (All) |
Underway - August 2024 |
|
Building A - Apartments G01-G02, 101-103, 201-203, 301-303, 401-403, 501-503 |
Late August 2024 |
|
Building A - Apartments G03-G04, 104-106, 204-206, 304-305, 404-405, 504-505 |
Early to mid September 2024 |
|
Building A - Apartments G05-G08, 107-109, 207-209, 306-308, 406-408, 506-508 |
Early to mid September 2024 |
|
Building A - Apartments G09-G10, 110-112, 210-212, 309-311, 409-411, 509-511 |
Mid to late September 2024 |
|
Building A - Apartments G11-G13, 113-115, 213-215, 312-314, 412-414, 512-514 |
Mid to late September 2024 |
If you have any questions, our Customer Care team are always available.
Site Safety
We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.
See more construction updates on