Shell Cove Construction Update - Nautilus Apartments
Nautilus – July 2024
Welcome to the latest Construction Update.
We’re pleased to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.
Building A
Internal fit-out works are effectively complete to all apartments with some final joinery elements being installed, detailing and final painting from West (Core A1) to East (Core A5).
Finishes and cleaning crews are now working through the building in preparation for Frasers Property’s next round of Quality Assurance checks.
Quality Assurance inspections by the Frasers Property team have been completed on Level 3 and quality inspections now underway on Levels 4 and 5. These inspections are an integral part of our commitment to delivering a high-quality project that meets industry standards.
Level 4 north west facing balcony view
Building A Master bedroom
Building A – Ensuite Dune colour scheme
Building A – Ensuite Dune colour scheme
Building A Living area
Building A Bathroom Mist colour scheme
Building B
Pre-settlement inspections (PSI) have now all been completed.
Building B Kitchen & living area
Building B – Bathroom Dune colour scheme
Building B Level 3 balcony view
Podium & verge works
The pool and associated commissioning including heat pumps and water quality testing is complete.
Nautilus Pool
All final asphalt layers have now been placed with line marking imminent. The Contractor is demobilising their site accommodation in preparation for handover.
Asphalt layers placed & line marking imminent
Nautilus – Birds eye view
Inspections by the building certifier are complete and the fire brigade completed their inspection on Tuesday 25 June 2024.
The building certifier has been issued majority of the Occupation Certificate documentation for their review in preparation for issue of the Occupation Certificate.
Settlement Update
We anticipate settlements to occur from August 2024 through to September 2024.
The below table outlines more detailed information on forecasted timings for when key milestones are anticipated to occur in the lead up to the settlement of your apartment in both Building's A and B.
Rotate your device: Please rotate your device to landscape mode for the best viewing experience of this table. This will ensure all details are clearly visible and the table is easier to navigate.
NAUTILUS PROGRAM AND TIMINGS |
BUILDING A |
BUILDING B |
Construction Phase |
||
Kitchens and Joinery Installation |
Underway |
Complete |
Frasers Property Quality Assurance Inspections |
Underway - up to level 4 |
Complete |
External Works |
Complete |
Complete |
Pre-settlement Phase |
||
Strata Plan Registration |
Registered |
Registered |
Pre Settlement Inspection Invitations |
August 2024 |
Complete |
Pre Settlement Inspections |
August 2024 |
Complete |
Valuations |
Throughout July 2024 |
Underway |
Occupation Certificate |
Mid July 2024 |
Mid July 2024 |
Settlement Phase |
||
Building B (All) |
Early August 2024 |
|
Building A - Apartments G01-G02, 101-103, 201-203, 301-303, 401-403, 501-503 |
Late August 2024 |
|
Building A - Apartments G03-G04, 104-106, 204-206, 304-305, 404-405, 504-505 |
Early to mid September 2024 |
|
Building A - Apartments G05-G08, 107-109, 207-209, 306-308, 406-408, 506-508 |
Early to mid September 2024 |
|
Building A - Apartments G09-G10, 110-112, 210-212, 309-311, 409-411, 509-511 |
Mid to late September 2024 |
|
Building A - Apartments G11-G13, 113-115, 213-215, 312-314, 412-414, 512-514 |
Mid to late September 2024 |
If you have any questions, our Customer Care team are always available.
Site Safety
We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.
See more construction updates on