Shell Cove Construction Update - Nautilus Apartments


10 July 2024

Nautilus – July 2024

Welcome to the latest Construction Update.

We’re pleased to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.

Building A

Internal fit-out works are effectively complete to all apartments with some final joinery elements being installed, detailing and final painting from West (Core A1) to East (Core A5).

Finishes and cleaning crews are now working through the building in preparation for Frasers Property’s next round of Quality Assurance checks.

Quality Assurance inspections by the Frasers Property team have been completed on Level 3 and quality inspections now underway on Levels 4 and 5. These inspections are an integral part of our commitment to delivering a high-quality project that meets industry standards.


Level 4 north west facing balcony view


Building A Master bedroom


Building A – Ensuite Dune colour scheme


Building A – Ensuite Dune colour scheme


Building A Living area


Building A Bathroom Mist colour scheme

Building B

Pre-settlement inspections (PSI) have now all been completed.


Building B Kitchen & living area


Building B – Bathroom Dune colour scheme


Building B Level 3 balcony view

Podium & verge works

The pool and associated commissioning including heat pumps and water quality testing is complete.


Nautilus Pool

All final asphalt layers have now been placed with line marking imminent. The Contractor is demobilising their site accommodation in preparation for handover.


Asphalt layers placed & line marking imminent


Nautilus – Birds eye view

Inspections by the building certifier are complete and the fire brigade completed their inspection on Tuesday 25 June 2024.

The building certifier has been issued majority of the Occupation Certificate documentation for their review in preparation for issue of the Occupation Certificate.

Settlement Update

We anticipate settlements to occur from August 2024 through to September 2024.

The below table outlines more detailed information on forecasted timings for when key milestones are anticipated to occur in the lead up to the settlement of your apartment in both Building's A and B.

 Rotate your device: Please rotate your device to landscape mode for the best viewing experience of this table. This will ensure all details are clearly visible and the table is easier to navigate.

NAUTILUS PROGRAM AND TIMINGS
BUILDING A
BUILDING B

Construction Phase

Kitchens and Joinery Installation

Underway

Complete

Frasers Property Quality Assurance Inspections

Underway - up to level 4

Complete

External Works

Complete

Complete

Pre-settlement Phase

Strata Plan Registration

Registered

Registered

Pre Settlement Inspection Invitations

August 2024

Complete

Pre Settlement Inspections

August 2024

Complete

Valuations

Throughout July 2024

Underway

Occupation Certificate

Mid July 2024

Mid July 2024

Settlement Phase

Building B (All)

Early August 2024

Building A - Apartments G01-G02, 101-103, 201-203, 301-303, 401-403, 501-503

Late August 2024

Building A - Apartments G03-G04, 104-106, 204-206, 304-305, 404-405, 504-505

Early to mid September 2024

Building A - Apartments G05-G08, 107-109, 207-209, 306-308, 406-408, 506-508

Early to mid September 2024

Building A - Apartments G09-G10, 110-112, 210-212, 309-311, 409-411, 509-511

Mid to late September 2024

Building A - Apartments G11-G13, 113-115, 213-215, 312-314, 412-414, 512-514

Mid to late September 2024

If you have any questions, our Customer Care team are always available.

Site Safety

We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.


Silvana Stojanovski Customer Care Coordinator Frasers Property Australia