myFrasersProperty 13 38 38
myFrasersProperty 13 38 38

Shell Cove Construction Update - Nautilus Apartments


17 June 2024
Central Place Sydney

L1 podium & pool now filled with water

Welcome to the latest Construction Update.

We’re pleased to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.

Building A

Frasers Property has completed their next round of Quality Assurance checks on Ground Floor.


Building A - Kitchen


Building A - Laundry


Ground floor main entrance


Building A - The breezeway

Internal fit-out works are effectively complete to all apartments with detailing and final painting of the respective lift lobbies and corridors underway.

Apartment wayfinding and statutory signage is being installed and will be completed in the coming days.

Finishes and cleaning crews are now working through the building in preparation for Frasers Property Australia’s next round of Quality Assurance checks.

The basement lobbies have been completed with feature rubber flooring and striking paint colours to the different lobbies to assist in wayfinding for residents and visitors

Quality Assurance inspections by the Frasers Property team are now underway on Level 3, with further quality inspections scheduled to start on Levels 4 and 5 in the coming weeks. These inspections are an integral part of our commitment to delivering a high-quality project that meets industry standards.

Building B

All apartments are now completed including Frasers Property's Quality Assurance inspections for Building B. The Customer Care team are currently contacting purchasers to book pre-settlement inspections (PSI).


Building B - Kitchen


Building B - Gym

Podium & verge works

The pool has now been filled with water and the associated commissioning and water quality testing to be completed by mid-June.

All terrace fences and gates are now completed with intercoms and access control systems commissioned. Inspections by the building certifier are ongoing and the fire brigade is scheduled to inspect in mid-June.


Terrace planters & feature lighting


Quayside Ave asphalt final road surface

Quayside Avenue has had its final asphalt surface layer placed. The Promontory Drive final asphalt layer will be placed by mid-June, following which the road will be line marked and the perimeter fencing removed once the Occupation Certificate is obtained and settlements near.


Nautilus illuminated by the full moon


Nautilus – June 2024

Settlement Update

We anticipate settlements to occur from August 2024 through to September 2024.

The below table outlines more detailed information on forecasted timings for when key milestones are anticipated to occur in the lead up to construction completing within both Building A and B, as well as forecasted timings to prepare for settlement of your apartment.

These forecasted timings will be reviewed as construction nears completion and we get closer to preparing your apartment for settlement.

 NAUTILUS PROGRAM AND TIMINGS 
BUILDING A
BUILDING B

Construction Phase

Kitchens and Joinery Installation

Underway

Complete

Frasers Property Quality Assurance Inspections

Underway - up to level 3

Complete

External Works

Complete late June 2024

Complete late June 2024

Pre-settlement Phase

Strata Plan Registration

Registered

Registered

Pre Settlement Inspection Invitations

August 2024

All invites sent

Pre Settlement Inspections

August 2024

17th to 28th June 2024

Valuations

Throughout July 2024

Throughout June 2024

Occupation Certificate

Mid July 2024

Mid July 2024

Settlement Phase

Building B (All)

Early August 2024

Building A - Apartments G01-G02, 101-103, 201-203, 301-303, 401-403, 501-503

Late August 2024

Building A - Apartments G03-G04, 104-106, 204-206, 304-305, 404-405, 504-505

Early to mid September 2024

Building A - Apartments G05-G08, 107-109, 207-209, 306-308, 406-408, 506-508

Early to mid September 2024

Building A - Apartments G09-G10, 110-112, 210-212, 309-311, 409-411, 509-511

Mid to late September 2024

Building A - Apartments G11-G13, 113-115, 213-215, 312-314, 412-414, 512-514

Mid to late September 2024

If you have any questions, our Customer Care team are always available.

Site Safety

We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.


Silvana Stojanovski Customer Care Coordinator Frasers Property Australia

See more construction updates on



You may also like