Five Farms Construction Update – Stage 28


27 March 2025

 

Settlement Forecast: June - July 2025

On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.

Construction Milestone: Authority Approvals
On Track

Prior to obtaining Statement of Compliance on Stage 28, the Precinct 2 Temporary Retarding Basin needs to be constructed, and acceptance of works granted.

Construction works on the Precinct 2 Temporary Retarding Basin are progressing well and are scheduled for completion in late May to early June 2025.

Once the construction works are complete and the respective authorities have given their approval, the process of obtaining Statement of Compliance on Stage 28 can be finalised.

With settlement fast approaching, we strongly encourage you to ensure your finance is in order, so that the settlement process goes as smooth as possible.


Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

We're available to discuss any questions or concerns you may have regarding your coming settlement.