Five Farms Construction Update – Stage 23


21 February 2024
Central Place Sydney

Construction Update

Welcome to the latest Five Farms Construction Update.

We are excited to keep you informed about how the Project is progressing, give you insights into the construction process and ensure you are up to date with the development of your new community.

Construction Progress

The Five Farms team are pleased to advise that Statement of Compliance has been achieved and Titles issued. Settlement will occur from 6 March 2024. Please contact our friendly Customer Care team should you have any questions.

Settlement Forecast

Settlement of your land is now anticipated in March 2024.

Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.

Helpful Links

Builder Information

Meet & Greet

We're available to discuss any questions or concerns you may have regarding your coming settlement.

Book your appointment now


See more construction updates on



You may also like