Berwick Waters Construction Update - Stage 16
- Settlement will occur on July 2025 – September 2025
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.- Construction Milestone: In progress
-
On Track
Construction of the kerb along the bridge suffered some delays but has recommenced. We are investigating opportunities to improve our programmed activities after kerb to attempt to hold the possibility of a settlement date in July 2025.
Within the main, internal, part of Stage 16 all service connections including electrical and communications are now complete as is all footpath and rock wall works.
As the bridge reaches various milestones of completion this will allow us to progressively connect services to the surrounding service infrastructure.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on