Berwick Waters Construction Update - Stage 16
- Settlement will occur on June 2025 – August 2025
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.- Construction Progress: In progress
-
On Track
Abutments of the Bridge and retaining walls are now complete and construction of the kerb along the bridge is still ongoing.
Internal stage 16 kerb and base layer asphalt to the roads is now installed, and electrical and communications installation works are almost complete.
Footpath and rock wall works will be the focus in the lead up to Christmas.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on