Berwick Waters Construction Update - Stage 8
Construction Update
Welcome to the latest Berwick Waters Construction Update.
We’re excited to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.
Construction Progress
We're pleased to advise that kerb and channel works are now 50% complete and electrical works have now commenced onsite.
Over the coming weeks kerb and channel, electrical and telecommunications works are programmed for completion.
Track your property anytime, anywhere on our new myFrasersProperty app. See more: https://www.frasersproperty.com.au/Care-and-Rewards/MyFrasersProperty
Settlement Forecast
Settlement of your land is now anticipated in Nov 2023 - Jan 2024.
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.
Helpful Links
Builder InformationBerwick Waters Facebook Page
Berwick Waters Community Page
Meet & Greet
We're available to discuss any questions or concerns you may have regarding your coming settlement.
Book your appointment nowIf you have any queries at all regarding settlement, we encourage you to get in touch!
See more construction updates on