Berwick Waters Quarterly Update – March 2023


06 March 2023
Berwick Waters

Dear residents and community members,

As you know there are a wide range of infrastructure projects involved at Berwick Waters.

We’ve made good progress on some aspects and not as much progress as we’d like on others.

A number of activities are currently in planning so we can’t give a finite update on some of those but there are a number of pieces of good news.

Firstly, the Town Centre Stage 1 planning permit has been received by Mondous Property so the commencement of bulk earthworks is imminent.

Work continues on Frasers Property’s section of the new road connection – Honour Avenue from Macumba Drive to Soldiers Road. We’ve constructed base layers of the road including a base layer of asphalt, installed drainage and have completed the gutters. We anticipate completion of this section by mid-2023.

Progressing works on the new road upgrade to connect Soldiers Road to Bells Road has been more difficult due to rainfall last winter and this site being one of the lowest in the community. We’re still hopeful of completing this work before Christmas 2023, weather permitting.

We will continue to update residents of Berwick Waters via email and keep the community updated via Facebook. For the latest news on Berwick Waters, check out www.frasersproperty.com.au/VIC/Berwick-Waters/News.

We appreciate your patience and feedback, and we’ll continue to provide updates to the community.

Jill Lim, Development Director – Land, for Frasers Property Australia

 

Quarterly Update