Ed.Square Construction Update - Block E North


03 February 2025

We are pleased to bring you our next construction update for your new home in Brooklyn Row Block E North.

Since our last update, we have seen exciting progress.

Lots 13121-13132: We are pleased to see that the kitchen installations are complete. Wet area tiling is almost complete along with internal fix out with hydraulic fit off now underway. This will allow for the installation of kitchen splashbacks and shower screens to commence in the coming days.

Lots 13133-13144: The main floor tiling is complete and the kitchen installations are now underway. Waterproofing to wet areas is nearing completion and our renderers are progressing well to the facade. This will allow our tilers to commence wet area tiling in the coming days.

In the rear courtyards of both wings, the form workers are setting out planter boxes. This will then be formed and poured within the next few days.

It is currently anticipated that your new home will be completed in 2nd Quarter 2025.

Site Safety

We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.

If you have any queries, do not hesitate to reach out to the Customer Care Team at CustomerCareNSW@frasersproperty.com.au or by calling 13 86 88.


Brian Halpin Customer Care Coordinator Frasers Property Australia