Wallara Waters Construction Update - Stage 22
- Settlement Forecast: January/February 2025
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.- Construction Progress: Services
-
On Track
Stage 22 continues to progress at a steady rate.
Sewer, stormwater drainage, water & gas works are 95% complete.
Pavement construction has significantly advanced with asphalting occurring in key areas.
Kerb and channel and footpaths significantly advanced.
Electrical and telecommunications installation is now at 60% complete. Balance including services across culvert crossing to follow.
Taylors Creek culvert has the headwall bases concreted and wingwalls to be poured by end October 2024.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on