Wallara Waters Construction Update - Stage 22
- Settlement Forecast: Q1 2025
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.- Construction Progress: Services
-
On Track
The Wallara Waters team are pleased to advise that the Future school site has been handed over for construction.
Sewer, stormwater drainage, water & gas works are 95% complete.Pavement construction has significantly advanced with asphalting occurring in key areas.
Kerb and channel under construction.
Services trenching is underway with electrical cabling to follow.
The Culvert bridge base has poured, with Culvert units to be placed from late August 2024.