Wallara Waters Construction Update - Stage 22


25 July 2024

 

Settlement Forecast: Q1 2025

On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.

Construction Progress: Services
On Track

The Wallara Waters team are pleased to advise that site remediation works, and bulk earthworks have been completed in Stage 22 and on the future school site.

The Sewer and Stormwater drainage works are 95% complete. Sewer works are the first service to be laid as they require the deepest trenches, that can range from 3 to 6 metres deep. The sewer system will carry waste away from your house to a treatment facility. This step is crucial for ensuring sanitation and public health in your community. Drainage works refers to the concrete pipes for storm water that need to be laid in order to drain any excess rainwater. Pits will also be installed at various points. Proper drainage is essential to prevent flood and protect your property and all the infrastructure in your community.

Watermains and gas works are now 95% complete, which refers to the pressure mains which are installed to provide drinking water to your community and gas pipelines installed to service your land lot.

Pavement construction has commenced, and the construction layer and services conduits are complete. The capping layer is now 75% complete and crushed rock layer is also 75% complete.

The Culvert bridge construction has now commenced.


Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

We're available to discuss any questions or concerns you may have regarding your coming settlement.

Book your appointment now


See more construction updates on



You may also like