Five Farms Construction Update - Stages 1-4
Construction Update
Welcome to the latest Five Farms Construction Update.
We are excited to keep you informed about how the Project is progressing, give you insights into the construction process and ensure you are up to date with the development of your new community.
Construction Progress
The team at Five Farms are pleased to advise that construction / boring of the South East Water Outfall Sewer has commenced. The Outfall Sewer needs to be completed to allow your Lot to title. We continue to work with the approval Authorities in order to ensure Statement of Compliance is achieved by the forecasted date.
Settlement Forecast
Settlement of your land is now anticipated in March-April 2023.
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.
Settlement Seminar
This event is an opportunity to prepare for the settlement of your land by giving you all the information you need as you approach this exciting milestone.
Join our team of dedicated experts for an evening of helpful tips, project updates and a range of exclusive partner offers.
Date: Wednesday, 1st March
Time: 6pm - 7:30pm
Location: Bunjil Place - 2 Patrick Northeast Dr, Narre Warren VIC 3805
Helpful Links
Meet & Greet
We're available to discuss any questions or concerns you may have regarding your coming settlement.
If you have any queries at all regarding settlement, we encourage you to get in touch!