Mambourin Construction Update - Stage 18


07 December 2022

Mambourin | December 2022 | Stage 18

Construction Update

Welcome to the latest Mambourin Construction Update.
We’re excited to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.

Construction progress

  • Sewer construction is ongoing and is forecast to be completed in January 2023.
  • Drainage works will follow sewer completion.
  • The recent wet weather has limited our ability to excavate and construct the sewer outfall.

As a result, the forecast for your settlement has been updated.

Read more about construction milestones

Settlement forecast

Settlement of your land is anticipated for July-September 2023.
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.