Mambourin Construction Update - Stage 18


10 February 2023
Construction Update

Welcome to the latest Mambourin Construction Update.

We’re excited to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.

Construction Progress

Stormwater drainage construction is predominantly completed and the water reticulation works are forecast to commence in the next month.

Settlement Forecast

Settlement of your land is now anticipated in Jul-Sep 2023

Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.

Helpful Links

Builder Information

Mambourin Community Page

Meet & Greet

We're available to discuss any questions or concerns you may have regarding your coming settlement.

Book your appointment now

If you have any queries at all regarding settlement, we encourage you to get in touch!