Brookhaven Construction Update - The Sanctuary Release Two


04 April 2025

 

Settlement Forecast: Late Q3 2025

On Track

Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.

Construction Progress: Bulk Earth Works
On Track

Golding Contractors are making strong progress, with bulk earthworks and export activities continuing to advance.

Despite the significant rainfall from Cyclone Alfred, the site effectively managed the surplus water. The team conducted a thorough review of erosion and sediment controls to ensure no additional damage occurred.

Final tree clearing has now been completed, with only minor weeding and maintenance remaining for the retained vegetation.

In the coming month, earthworks will continue, alongside the commencement of retaining wall construction and service infrastructure installation.


Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

We're available to discuss any questions or concerns you may have regarding your coming settlement.