Wallara Waters Construction Update - Stage 16
Construction Update
Welcome to the latest Wallara Waters Construction Update.
We’re excited to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.
Construction Progress
Stage 16 bulk earthworks completed. Sewer reticulation works, drainage pit and pipeworks are complete. Timeframes for achieving Statement of Compliance remain on track for June 2023, with settlements to follow.
Settlement Forecast
Settlement of your land is now anticipated in June - July 2023.
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.
Helpful Links
Meet & Greet
We're available to discuss any questions or concerns you may have regarding your coming settlement.
If you have any queries at all regarding settlement, we encourage you to get in touch!
See more construction updates on