The Grove Construction Update – Stage 54


27 February 2025

 

Settlement Forecast: Dec 2025 - March 2026

On Track

Construction Progress: Services
On Track

We are pleased to advise that construction of Stage 54 is in progress and progressing well.

Bulk earthworks and sewer works are now complete, providing a solid foundation for your future home, roads, and essential infrastructure. The sewer system will efficiently carry waste to a treatment facility, ensuring proper sanitation and public health in your community.

The concrete pipes for stormwater drainage is near completion, these are installed to manage excess rainwater, with pits placed at key points to prevent flooding and protect both your property and surrounding infrastructure. Additionally, electrical trenching is underway.


Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

We're available to discuss any questions or concerns you may have regarding your coming settlement.

Book your appointment now


Tina Wu Senior Customer Care Consultant Melbourne

See more construction updates on



You may also like