Mambourin Construction Update - Stage 41


19 July 2024

 

Settlement Forecast: October - November 2024

On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.

Construction Progress: Final Works
On Track

Kerb and channel works are completed. Kerbs and channels are laid on the road profile. This is a critical step to ensure a well-designed road infrastructure and safety.

Asphalt base layers are complete. Base course asphalt is laid to provide a pavement structure of roads and driveways. Footpaths and vehicle crossovers are next installed to promote a well-connected, safe and functional community.

Track your property anytime, anywhere on our new myFrasersProperty app.

See more

Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

We're available to discuss any questions or concerns you may have regarding your coming settlement.


See more construction updates on



You may also like