Five Farms Construction Update – Allendale Residents' Club
- Planned Opening: November 2024
On Track
- Construction Progress: Top out scheduled
-
On Track
The Five Farms team is pleased to advise that construction of the Allendale Residents’ Club is progressing well.
Internally, the pool equipment installation is well underway, bathroom tiling is complete, and partitions have commenced. The gymnasium ceiling is installed and painted, and the rubber gym flooring has commenced.
In the main foyer, plastering is finished, and concrete polishing is expected to commence shortly. The café fit out is progressing well, with paint finishes complete, vinyl flooring underway, and kitchen equipment set to be installed in the coming weeks.
For any queries, do not hesitate to contact our helpful Customer Care team.
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on